451 (Development)                                     July 18, 1939.

Progress Report - Month Ending June 30, 1939 - Project EDT - No. 9-9 - Truck, Messenger, 3-Passenger.
The Quartermaster General, Washington, D. C.



June 30, 1939

a. Due to the pressure of other work no further progress has been made on this project.

H. J. LAWES,
Lieut. Colonel, Quartermaster Corps,
Commanding.